719-725 W. Pratt St. construction updates

Thursday, September 17, 2020

Start time update and next phases

Yesterday, a new contractor started welding at a very early hour. The developer was made aware of the problem, corrected it, and apologizes for the early morning interruption. Workers should not begin work prior to 7 a.m. The next phase of construction will be framing and masonry that will last until the end of the year. There will be periodic deliveries on Dover Street, but they will try to make them as quick as possible, and not block the street.

Wednesday, July 8, 2020

Length of excessive noise

The “piling” work will continue through Monday, July 13. There was also a water main break on Pratt so the city was using jackhammers to add to the noise. 

Tuesday, June 23, 2020

Dover Street cobblestones

The developers do not plan to disturb the cobblestone in the 700 block of Dover St. But if their plans have to change, they will save the stones and put them back the way they found them.